Required volume of Cement Mortar = plastering area x plastering thickness = 100 x 0.012 = 1.2 m 3. Adding Bulking of Sand & Wastage. So to get 1.2 m 3 of wet cement mortar, we have to multiply the dry volume by 1.55. What is 1.55 constant in the calculation? 1.
1- material. 2- labour charge. material means :1- concrete price and that depend of wat element u want to cast it sub or super struc. and is it required green concrete or SRC or OPC approxmately it will be around AEd255 if its green concrete. oAed 215 if it SRC for mix 400 kg grade 40 n. also pump charge will be assume 50/m3
Answer / sjtbehera. For M20 Grade conc. Head mason - .05 x Rs 200 = Rs 10.00 Mason - .3 x Rs 190 = Rs 57.00 Labour - 2.5 x Rs 90 = Rs 225 _____ Total amount - Rs 292.00
It doesn't include labor, supplies such as reinforcing bar, if needed, or building permit fees. At the time of publication, the average cost of concrete for a 400-square foot slab, the typical size for a two-car garage, ranges between $583 and $637 or between $1.46 and $1.59 per square foot.
Builders' Association of India(BAI) was formed in 1941 in Pune with guidance from Brigadier Jackson, who also allotted office space in the Military Compound. The then office of BAI, aptly named `Jackson Hut' in his memory, is still being used by BAI
One bag of cement and other ingredients can produce = 400/2400 = 0.167 Cum of concrete (1:2:4) 01 bag cement yield = 0.167 cum concrete with a proportion of 1:2:4. 01 cum of concrete will require. Cement required = 1/0.167 = 5.98 Bags ~ 6 Bags. Sand required = 115/0.167 = 688 Kgs or 14.98 cft. Aggregate required = 209/0.167 = 1251 kgs or 29.96 cft
Jul 25, 2018· Job Description for a Concrete Form Laborer. Because of its strength and durability, concrete is a popular building material for structures and highways. Concrete form laborers, also known as cement masons, are hired to ensure the concrete is poured and set the right way. Much of the work is outdoors and can only be ...
Apr 20, 2018· BrickWork Calculation & best automatic calculator to find quantity of bricks with or without mortar and you can also add thickness of RCC bed if required in calculation. Types of Bricks, How to calculate the no. of bricks required for 1 cubic meter, No. of bricks required in a wall.
Concrete Ingredients Calculation. For Cement, Sand and Coarse Aggregate. This is a Volumetric Calculation. Assuming we need 2 m 3 of concrete for M20 Concrete Mix, (Mix Ratio, M20 = 1 : 1.5 : 3) Total Part of the Concrete = 1+1.5+3 = 5.5 Parts. Therefore, Cement Quantity = (Cement Part / Concrete Parts ) * Concrete Volume
Calculate Volume of Square Slab Calculator Use. Calculate volumes for concrete slabs, walls, footers, columns, steps, curbs and gutters. Enter dimensions in US units (inches or feet) or metric units (centimeters or meters) of your concrete structure to get the cubic yards value of the amount of concrete you will need to make this structure.
The maximum reinforcement required is0.4% of the concrete area, as we know the area of reinforcement required according design using any code of standards is r*b*d.....where r---is the steel ratio, b----effective width of the section of the element and d-----is the depth from the top compression zone to the center of the reinforcement.
0.68 kg./sq.m on the entire landscape garden concrete slab and walls upto 300 mm above the top level of soil. WATERPROOFING-CUM-ROOT REPELLENT MEMBRANE: The sixth part consisting of providing and applying water-based, liquid-applied, 100% Polyurethane Flexible Waterproofing-cum .
Jul 21, 2018· Mason 3.7 days Labour 35 days Water carrier 13.9 days Bar bender 1 day/ 100 kg Mixer operator-0.72 days Vibrator operator0.72 days Day means 8 hours with lunch break of .
For slabs = 1.0 % of concrete volume. For Beam = 2 % concrete volume. For column = 2.5 % of concrete volume. For RCC Roads, 0.6% concrete volume. Lets take example of RCC Column, where reinforcement required is 2.5% of concrete volume, weight of steel required will be: =196.25 kg. 2. Labour Requirement for 1m 3 of RCC:
1. Precast Concrete Products, Bricks and Block Making Other sections to be included when developed Part 4 Labour-based construction technologies 1. Labour-based open channel flow technology 2. Rubble masonry concrete dam construction technology 3. Rubble masonry concrete arch bridge construction technology 4. Foamed bitumen gravel. 5.
As per the data the calulation goes like for 1 Cum Concrete the requirement of shuttering is 11.71813333 Sqm On concretable area for 1 Cum Concrete the requirement of shuttering is 3.767038414 Sqm On floor plate area Shuttering required for 1 Sqm on BUA 3.110701842 Sqm On BUA Concrete Coefficient / Sqm 3.767038414 Posted: 1857 days ago
For better illustration, we are going to use square metre unit throughout the post. Tile flooring process at glance, First, we need to fill the flooring area with cement mortar (1:4 ratio) at a minimum thickness (50 mm). we may increase the thickness of the cement sand mortar to adjust the height of the floor.
Labours required are presented in terms of days required by particular labour to complete its work for the given quantity of concrete. Following are the various labours required: Mason: As per Standard Schedule of Rates and Analysis of Rates, One mason is required for 0.37 days. Labours: One Unskilled labours required for 3.5 days. Water carrier:
0.36 skilled and 2 unskilled labour is enough form onc cum concrete. Is This Answer Correct ? 18 Yes : 4 No : how many labour is required for 1cum of concrete? .. Answer / ... per 1 cumt concrete how much manhours is required including shuttring,steel etc.,for slab & foundations .
Batching plant 2 x 1.5 cum per hour Rs: 357.00 225.00 62.80 Concrete bucket 1.5 cum Rs: 7.00 3.00 --- ... hidden cost on labour etc. 3. The basic rates are inclusive of royalty charges payable on materials. 4. The recovery of royalty charges on materials, wherever applicable, shall be as per the guide ... Unless otherwise specified the basic ...
Density of concrete = 2400 kg/cum. So, 1 bag of cement produces = 400/2400 = 0.167 cum. No. of bags required for 01 cum of concrete = 1/0.167 = 5.98 bags ~ 6 bags. From above, if the concrete mix is 1:2:4, to get a cubic meter of concrete we require. 1.Cement = 6 bags = 300 kgs. 2.Fine Aggregate = 115/0.167 = 689 kg
Dec 21, 2016· =0.0347 cum. ∴ No. of cement bags required in 1 cubic meter = 0.2171/0.0347 = 6.25 bags. Note: You can use the same formula for calculating cement for other nominal mixes. ... Any one please send mix design for m30 grade of concrete using 1%, 1.5%,2% crimped Steel and poly propylene fibres. Farjad January 25, 2018 at 3:19 pm. Reply. ...
Example calculation Estimate the quantity of cement, sand and stone aggregate required for 1 cubic meter of 1:2:4 concrete mix. Ans. Materials required are 7 nos. of 50 kg bag of cement, 0.42 m 3 of sand and 0.83 m 3 of stone aggregate.
Oct 12, 2018· Generally for slab we use M20 grade of concrete. Here M refer to Mix and 20 is the 28 days compressive strength in N/mm2. which is calculated by Cube testing. M20 => 1:1.5:3; as we assume by volume 1 vessel is cement, 1.5 vessel is sand and 3 vessel is aggregate. Note that all the vessel/container have same volume.